Progress of works on the crematorium

Update on the new crematorium

Works to date:

  • Fencing to site boundary installed
  • Temporary site establishment set up
  • Commencement of bulk earthworks operations
  • Top soil/vegetation strip/collection of timber debris
  • Removal of tree stumps
  • Formation of access on to site
  • Formation of roads

Works planned for next month:

  • Continuation of bulk earthworks operations
  • installation of roads
  • Installation of car park
  • Reduced level excavation to building footprint
  • Reduced level excavation to attenuation ponds
  • Tarmac to roads and car park
  • Commencement of ground works operations